Back to projects

Brigus Road Water and Sewer Upgrades

Whitbourne, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$485,618
Federal share35%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
2021
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Whitbourne
Construction start
Aug 16, 2021(actual)
Construction end
Nov 16, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2021
  • Construction end3 weeks earlyforecast Dec 5, 2021

Also in Whitbourne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56858 in the federal list. How to read these figures.