Watermain Upgrade - Whitbourne Avenue / Extension
Whitbourne, Newfoundland and Labrador
Federal contribution
$232,952
Federal share27%
of $855.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.9 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Whitbourne
- Construction start
- May 22, 2009(actual)
- Construction end
- Dec 31, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 15, 2009
- Construction end2.1 years lateforecast Nov 30, 2009