Back to projects

Opera House/Town Hall

Battleford, Saskatchewan

completeCultureMRIF
Federal contribution
$125,000
Federal share25%

of $505.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 1, 2008
200820092010
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Battleford
Construction start
Dec 14, 2007(actual)
Construction end
Dec 7, 2009(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2010

Also in Battleford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18681 in the federal list. How to read these figures.