Water System Upgrades
Federal contribution
$73,472
Federal share33%
of $220.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2008
2009
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Middleton
- Construction start
- Jan 28, 2008(actual)
- Construction end
- Aug 25, 2009(actual)
Against the original forecast
- Construction start2.2 years lateforecast Nov 24, 2005
- Construction end7 months earlyforecast Mar 31, 2010
Also in Middleton