Middleton's Transportation Master Plan

Middleton, Nova Scotia

completeCapacity BuildingATF
Federal contribution
$35,000
Federal share100%

of $35.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
20232024
Built

Approved 20 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Middleton
Construction start
Jun 1, 2023(actual)
Construction end
May 21, 2024(actual)

Against the original forecast

  • Construction start12 months lateforecast May 31, 2022
  • Construction end18 months lateforecast Nov 29, 2022