Wastewater Treatment Plant Replacement
Federal contribution
$1.3M
$1,312,300
Federal share33%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 28, 2009
200920102011
Built
Approved 2 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Middleton
- Construction start
- Nov 2, 2009(actual)
- Construction end
- Aug 30, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2009
- Construction end2 months lateforecast Jun 30, 2011
Also in Middleton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26801 in the federal list. How to read these figures.