Main Street Sewer Line Replacement
Federal contribution
$297,266
Federal share29%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 28, 2015
201620172018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Middleton
- Construction start
- May 11, 2020(actual)
- Construction end
- Oct 23, 2020(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 1, 2019
- Construction end7 months lateforecast Mar 31, 2020
Also in Middleton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46040 in the federal list. How to read these figures.