Construction of a New Water Storage Facility
Federal contribution
$1.1M
$1,118,789
Federal share33%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 22, 2008
200920102011
Built
Approved 2 weeks after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Midland
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start12 months lateforecast May 28, 2008
- Construction end17 months earlyforecast Mar 31, 2013
Also in Midland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19714 in the federal list. How to read these figures.