Municipal Office Expansion/Retrofit

Midland, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$1.3M
$1,333,333
Federal share33%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Midland
Construction start
Apr 19, 2010(actual)
Construction end
Aug 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 1, 2010
  • Construction end2 months earlyforecast Oct 31, 2011