Highway 12 Chlorine Contact Main Replacement

Midland, Ontario

completeDrinking WaterCWWF
Federal contribution
$475,000
Federal share32%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2018
201920202021
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Midland
Construction start
Nov 29, 2018(actual)
Construction end
Feb 25, 2021(actual)

Against the original forecast

  • Construction start7 months lateforecast May 1, 2018
  • Construction end5 weeks earlyforecast Mar 31, 2021