Back to projects

Town of Midland Transit Vehicle Replacement

Midland, Ontario

completePublic TransitPTIS
Federal contribution
$286,000
Federal share51%

of $559.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 18, 2020
2021
Built

Approved 6 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
Town of Midland
Construction start
Apr 1, 2020(actual)
Construction end
Mar 31, 2021(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Apr 30, 2021

Also in Midland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55067 in the federal list. How to read these figures.