Construction of Watermains

Dawn-Euphemia, Ontario

completeDrinking WaterMRIF
Federal contribution
$75,288
Federal share33%

of $225.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2008
2009201020112012
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Dawn-Euphemia
Construction start
May 28, 2008(actual)
Construction end
Mar 1, 2012(actual)

Against the original forecast

  • Construction end13 months earlyforecast Mar 31, 2013