Public Work's Maintenance/Repair Shop Addition

Dawn-Euphemia, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Dawn-Euphemia
Construction start
Sep 12, 2022(actual)
Construction end
Jun 13, 2023(actual)

Against the original forecast

  • Construction end6 months lateforecast Dec 23, 2022