Watermain - Lambton Line-Dawn Valley
Federal contribution
$274,000
Federal share33%
of $822.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Dawn-Euphemia
- Construction start
- Jul 26, 2010(actual)
- Construction end
- Jun 10, 2011(actual)
Against the original forecast
- Construction start8 months lateforecast Nov 30, 2009
- Construction end3 weeks earlyforecast Jun 30, 2011
Also in Dawn-Euphemia