Back to projects

Replacement of 350 Water System Meters

Dawn-Euphemia, Ontario

completeDrinking WaterCWWF
Federal contribution
$50,000
Federal share36%

of $140.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020202120222023
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Dawn-Euphemia
Construction start
Sep 1, 2017(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start9 months lateforecast Nov 30, 2016
  • Construction end9 months lateforecast Apr 15, 2022

Also in Dawn-Euphemia

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48618 in the federal list. How to read these figures.