Replacement of 350 Water System Meters
Federal contribution
$50,000
Federal share36%
of $140.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201820192020202120222023
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Dawn-Euphemia
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start9 months lateforecast Nov 30, 2016
- Construction end9 months lateforecast Apr 15, 2022
Also in Dawn-Euphemia
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48618 in the federal list. How to read these figures.