Bible Hill Water System Extension
Federal contribution
$360,400
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2008
20092010
Built
Approved 7 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Bible Hill
- Construction start
- May 31, 2010(actual)
- Construction end
- Sep 15, 2010(actual)
Against the original forecast
- Construction start21 months lateforecast Sep 1, 2008
- Construction end6 months earlyforecast Mar 31, 2011
Also in Bible Hill
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22359 in the federal list. How to read these figures.