Guest drive storm sewer upgrades Phase II
Federal contribution
$526,274
Federal share45%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Bible Hill
- Construction start
- Jun 5, 2017(actual)
- Construction end
- Nov 15, 2017(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jul 1, 2017
- Construction end2 weeks earlyforecast Nov 30, 2017
Also in Bible Hill
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47215 in the federal list. How to read these figures.