Storm Sewer Realignment - Guest Drive

Bible Hill, Nova Scotia

completeWastewaterCC
Federal contribution
$241,667
Federal share33%

of $725.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20122013201420152016
Built

Approved 4.6 years before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Bible Hill
Construction start
May 15, 2012(actual)
Construction end
Aug 14, 2012(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Jul 1, 2012

Also in Bible Hill

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27013 in the federal list. How to read these figures.