Sanitary and Storm Sewer Realignment
Federal contribution
$271,807
Federal share33%
of $815.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 23, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Bible Hill
- Construction start
- Oct 6, 2010(actual)
- Construction end
- Mar 17, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 15, 2010
- Construction end2 weeks earlyforecast Mar 31, 2011
Also in Bible Hill
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36961 in the federal list. How to read these figures.