Watermain Upgrade - Longhill Road

Mahone Bay, Nova Scotia

completeDrinking WaterCC
Federal contribution
$50,729
Federal share33%

of $152.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2008
20092010
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Mahone Bay
Construction start
Aug 5, 2009(actual)
Construction end
Dec 15, 2009(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2009
  • Construction end15 months earlyforecast Mar 31, 2011