Oak Bay - Beach Drive Upgrade

Victoria, British Columbia

completeHighways and RoadsCC
Federal contribution
$160,437
Federal share33%

of $490.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 27, 2009
Built

Approved 3 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
District of Oak Bay
Construction start
Aug 7, 2009(actual)
Construction end
Oct 21, 2009(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Sep 30, 2009

Also in Victoria

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22444 in the federal list. How to read these figures.