Road Upgrade - West Street

St. Anthony, Newfoundland and Labrador

completeHighways and RoadsMRIF
Federal contribution
$138,584
Federal share33%

of $415.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of St. Anthony
Construction start
Sep 9, 2010(actual)
Construction end
Mar 29, 2012(actual)

Against the original forecast

  • Construction start14 months lateforecast Jul 1, 2009
  • Construction end2.5 years lateforecast Oct 1, 2009