Road Upgrade - West Street
St. Anthony, Newfoundland and Labrador
Federal contribution
$138,584
Federal share33%
of $415.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.8 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of St. Anthony
- Construction start
- Sep 9, 2010(actual)
- Construction end
- Mar 29, 2012(actual)
Against the original forecast
- Construction start14 months lateforecast Jul 1, 2009
- Construction end2.5 years lateforecast Oct 1, 2009
Also in St. Anthony
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22517 in the federal list. How to read these figures.