Water Main Replacement

St. Anthony, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$1.3M
$1,344,908
Federal share48%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of St. Anthony
Construction start
Jul 4, 2017(actual)
Construction end
Dec 14, 2017(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2018

Also in St. Anthony

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47067 in the federal list. How to read these figures.