West Street Waterline Upgrading

St. Anthony, Newfoundland and Labrador

underwayDrinking WaterGIS
Federal contribution
$1.3M
$1,342,051
Federal share40%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
202420252026
BuiltForecast

Approved 23 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Anthony
Construction start
Aug 6, 2025(actual)
Construction end
Jul 31, 2026(forecast)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2025