West Street Waterline Upgrading
St. Anthony, Newfoundland and Labrador
Federal contribution
$1.3M
$1,342,051
Federal share40%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
202420252026
BuiltForecast
Approved 23 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Anthony
- Construction start
- Aug 6, 2025(actual)
- Construction end
- Jul 31, 2026(forecast)
Against the original forecast
- Construction start3 months lateforecast May 1, 2025
Also in St. Anthony