Water Line Upgrade North Street
St. Anthony, Newfoundland and Labrador
Federal contribution
$510,476
Federal share40%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Anthony
- Construction start
- Jun 27, 2022(actual)
- Construction end
- Sep 23, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 7, 2022
- Construction end5 weeks earlyforecast Oct 31, 2022
Also in St. Anthony