Fort St. John - Wastewater Treatment Plant Upgrades
Fort St. John, British Columbia
Federal contribution
$842,333
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 19, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Fort St. John
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Dec 31, 2011(actual)