Highway 97 - South Taylor Hill
Fort St. John, British Columbia
Federal contribution
$10.8M
$10,750,000
Federal share50%
of $21.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 28, 2013
ApprovedAug 20, 2013
201420152016
Built
Approved 5 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of British Columbia
- Construction start
- Jul 4, 2014(actual)
- Construction end
- Oct 5, 2016(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 15, 2014
- Construction end8 weeks earlyforecast Nov 30, 2016
Also in Fort St. John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44306 in the federal list. How to read these figures.