Back to projects

Highway 97 - South Taylor Hill

Fort St. John, British Columbia

completeHighways and RoadsMIC
Federal contribution
$10.8M
$10,750,000
Federal share50%

of $21.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 28, 2013
ApprovedAug 20, 2013
201420152016
Built

Approved 5 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Jul 4, 2014(actual)
Construction end
Oct 5, 2016(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 15, 2014
  • Construction end8 weeks earlyforecast Nov 30, 2016

Also in Fort St. John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44306 in the federal list. How to read these figures.