Fort St. John - Enerplex Site Improvements

Fort St. John, British Columbia

completeSportCC Top Up
Federal contribution
$2.5M
$2,505,899
Federal share33%

of $7.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Fort St. John
Construction start
Nov 2, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Oct 15, 2009

Also in Fort St. John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27942 in the federal list. How to read these figures.