North Peace Side Road Improvements - Phase 2

Fort St. John, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.9M
$1,893,028
Federal share50%

of $3.8M total eligible cost; the rest comes from other partners.

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 16, 2010(actual)
Construction end
Oct 25, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 1, 2010
  • Construction end8 weeks lateforecast Sep 1, 2010

Also in Fort St. John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41219 in the federal list. How to read these figures.