Back to projects

Siphon Creek Road

Fort St. John, British Columbia

completeHighways and RoadsISF
Federal contribution
$2.3M
$2,339,558
Federal share50%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 19, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
Jul 28, 2010(actual)
Construction end
Sep 26, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 28, 2010
  • Construction end5 weeks earlyforecast Oct 31, 2010

Also in Fort St. John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39398 in the federal list. How to read these figures.