Siphon Creek Road
Fort St. John, British Columbia
Federal contribution
$2.3M
$2,339,558
Federal share50%
of $4.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 19, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jul 28, 2010(actual)
- Construction end
- Sep 26, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 28, 2010
- Construction end5 weeks earlyforecast Oct 31, 2010
Also in Fort St. John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39398 in the federal list. How to read these figures.