Back to projects

Sanitary Sewer System Replacement

Harbour Breton, Newfoundland and Labrador

completeWastewaterMRIF
Federal contribution
$230,813
Federal share33%

of $693.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Harbour Breton
Construction start
Jun 2, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 1, 2009
  • Construction end12 months lateforecast Nov 30, 2009

Also in Harbour Breton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22637 in the federal list. How to read these figures.