Bay d'Leau Drive North Water Main Replacement

Harbour Breton, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$660,720
Federal share40%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
2023202420252026
Built

Approved 3.4 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Harbour Breton
Construction start
Jul 2, 2024(actual)
Construction end
Nov 9, 2024(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 23, 2024
  • Construction end7 months earlyforecast May 30, 2025