Chlorine Booster Station
Harbour Breton, Newfoundland and Labrador
Federal contribution
$142,003
Federal share27%
of $535.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2018
201920202021
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Harbour Breton
- Construction start
- Jul 1, 2020(actual)
- Construction end
- Jun 30, 2021(actual)
Against the original forecast
- Construction end9 months earlyforecast Mar 31, 2022
Also in Harbour Breton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52209 in the federal list. How to read these figures.