Back to projects

Upgrading Storm and Sewer Infrastructure - Godwin's Hill/Canada Drive, Harbour Breton

Harbour Breton, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$397,668
Federal share40%

of $994.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2021
2021
Built

Approved 13 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Harbour Breton
Construction start
Jun 1, 2021(actual)
Construction end
Oct 31, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2021
  • Construction end4 weeks lateforecast Oct 1, 2021

Also in Harbour Breton