Back to projects

Village of McAdam Wastewater, Lake, Sewage Separation Study

McAdam, New Brunswick

completeCapacity BuildingCC
Federal contribution
$30,328
Federal share33%

of $91.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 27, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of McAdam
Construction start
May 1, 2009(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Jun 10, 2009
  • Construction end3 months lateforecast Mar 31, 2010

Also in McAdam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22981 in the federal list. How to read these figures.