Bridal Falls (Electoral Area D) - Integrated Water System
Federal contribution
$879,568
Federal share32%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Regional District of Fraser Valley
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Mar 31, 2012(actual)
Against the original forecast
- Construction start6 months lateforecast Sep 24, 2009
Also in Chilliwack
- Vedder Bridge Replacement$4.2M
- Chilliwack - Design and Construction of Organic Food Waste Receiving and Pre-Processing Station & Digester # 4$3.6M
- City of Chilliwack Wastewater Treatment Plant Biological Treatment Expansion Phase 2$3.6M
- Replacement of Sanitary Sewers$1.3M
- Chilliwack - Evans Road Connector$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22997 in the federal list. How to read these figures.