Replacement of Sanitary Sewers
Federal contribution
$1.3M
$1,266,666
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 16, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 6 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Chilliwack
- Construction start
- Jun 9, 2010(actual)
- Construction end
- Apr 9, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 5, 2010
- Construction end7 weeks earlyforecast May 31, 2011
Also in Chilliwack
- Vedder Bridge Replacement$4.2M
- Chilliwack - Design and Construction of Organic Food Waste Receiving and Pre-Processing Station & Digester # 4$3.6M
- City of Chilliwack Wastewater Treatment Plant Biological Treatment Expansion Phase 2$3.6M
- Chilliwack - Evans Road Connector$1.0M
- Chilliwack - West Dike Upgrades, Left Bank$948.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39423 in the federal list. How to read these figures.