Vedder Bridge Replacement
Federal contribution
$4.2M
$4,187,916
Federal share33%
of $12.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 10, 2015
201620172018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Chilliwack
- Construction start
- Aug 1, 2016(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction end11 months earlyforecast Oct 31, 2018
Also in Chilliwack
- Chilliwack - Design and Construction of Organic Food Waste Receiving and Pre-Processing Station & Digester # 4$3.6M
- City of Chilliwack Wastewater Treatment Plant Biological Treatment Expansion Phase 2$3.6M
- Replacement of Sanitary Sewers$1.3M
- Chilliwack - Evans Road Connector$1.0M
- Chilliwack - West Dike Upgrades, Left Bank$948.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46142 in the federal list. How to read these figures.