Chilliwack - West Dike Upgrades, Left Bank

Chilliwack, British Columbia

completeDisaster MitigationCC Top Up
Federal contribution
$948,115
Federal share29%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Chilliwack
Construction start
Aug 3, 2010(actual)
Construction end
Oct 21, 2010(actual)

Against the original forecast

  • Construction start10 months lateforecast Sep 28, 2009
  • Construction end5 months earlyforecast Mar 31, 2011