City of Chilliwack Wastewater Treatment Plant Biological Treatment Expansion Phase 2
Federal contribution
$3.6M
$3,566,240
Federal share40%
of $8.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2024
today
202420252026
BuiltForecast
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Chilliwack
- Construction start
- Sep 27, 2024(actual)
- Construction end
- Sep 11, 2026(forecast)
Against the original forecast
- Construction start4 weeks lateforecast Aug 30, 2024
Also in Chilliwack
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66769 in the federal list. How to read these figures.