City of Chilliwack Wastewater Treatment Plant – Biological Treatment Expansion – Phase 2

Chilliwack, British Columbia

underwayWastewaterGIS
Federal contribution
$3.6M
$3,566,240
Federal share40%

of $8.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 22, 2024
today
202420252026
BuiltForecast

Approved 8 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Chilliwack
Construction start
Sep 27, 2024(actual)
Construction end
Sep 11, 2026(forecast)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 30, 2024

Also in Chilliwack

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66769 in the federal list. How to read these figures.