Development of Mitchell Domestic Landfill Site
Federal contribution
$1.1M
$1,076,015
Federal share33%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of West Perth
- Construction start
- May 16, 2011(actual)
- Construction end
- Dec 16, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2011
- Construction end6 weeks lateforecast Nov 1, 2011