Herbert Street Pumping Station

Mitchell, Ontario

completeWastewaterISF
Federal contribution
$62,667
Federal share32%

of $193.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2011
2011
Built

Approved 8 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of West Perth
Construction start
Feb 18, 2011(actual)
Construction end
Oct 27, 2011(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Mar 30, 2011
  • Construction end4 weeks lateforecast Sep 30, 2011