Reconstruction of Wellington Street North

Mitchell, Ontario

completeDrinking WaterCC Top Up
Federal contribution
$617,463
Federal share33%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Municipality of West Perth
Construction start
Mar 23, 2010(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Oct 31, 2011