Back to projects

Mitchell Emergency Management System Base

Mitchell, Ontario

completeHealthcare InfrastructureISF
Federal contribution
$310,000
Federal share33%

of $930.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Perth
Construction start
Nov 6, 2009(actual)
Construction end
Jul 9, 2010(actual)