Water & Sewer Extension Beresford Industrial Park
Federal contribution
$395,106
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2009
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Beresford
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Dec 15, 2009(actual)
Against the original forecast
- Construction start4 months lateforecast May 18, 2009
- Construction end7 weeks lateforecast Oct 30, 2009
Also in Beresford
- Beresford - Sanitary Outfalls Reduction in Beresford Wetlands$2.7M
- Foulem Subdivision: Replacement of Sanitary and Water Supply Systems$1.2M
- Looping of drinking water network$262.8K
- Water and Wastewater System Improvements$153.4K
- Replacement of the aqueduct and sanitary system in Maurice and Luc streets$139.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23047 in the federal list. How to read these figures.