Replacement of the aqueduct and sanitary system in Maurice and Luc streets
Federal contribution
$139,641
Federal share47%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2018
2018
Built
Approved 13 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Beresford
- Construction start
- May 15, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Jul 4, 2017
- Construction end8 months earlyforecast Jul 31, 2019
Also in Beresford