Back to projects

Replacement of the aqueduct and sanitary system in Maurice and Luc streets

Beresford, New Brunswick

completeWastewaterCWWF
Federal contribution
$139,641
Federal share47%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2018
2018
Built

Approved 13 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Beresford
Construction start
May 15, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Jul 4, 2017
  • Construction end8 months earlyforecast Jul 31, 2019

Also in Beresford