Beresford - Sanitary Outfalls Reduction in Beresford Wetlands

Beresford, New Brunswick

completeWastewaterGIS
Federal contribution
$2.7M
$2,743,060
Federal share40%

of $6.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 17, 2022
20222023
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Beresford
Construction start
May 23, 2022(actual)
Construction end
Nov 3, 2023(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 2, 2022
  • Construction end11 months earlyforecast Sep 30, 2024

Also in Beresford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62269 in the federal list. How to read these figures.