Back to projects

Foulem Subdivision: Replacement of Sanitary and Water Supply Systems

Beresford, New Brunswick

completeWastewaterCWWF
Federal contribution
$1.2M
$1,208,706
Federal share50%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Beresford
Construction start
May 14, 2017(actual)
Construction end
Aug 23, 2019(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jun 1, 2017
  • Construction end3 weeks lateforecast Jul 31, 2019