Well House Residual Chlorination Monitoring
Federal contribution
$8,447
Federal share33%
of $25.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 27, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of McAdam
- Construction start
- Jul 15, 2009(actual)
- Construction end
- Sep 30, 2009(actual)
Against the original forecast
- Construction start2 months lateforecast May 15, 2009
- Construction end2 months lateforecast Jul 31, 2009