Back to projects

Water and Sewer Installation on West Street

McAdam, New Brunswick

completeDrinking WaterCC Top Up
Federal contribution
$63,867
Federal share33%

of $191.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2009
2010
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of McAdam
Construction start
Aug 16, 2010(actual)
Construction end
Sep 30, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2010

Also in McAdam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23072 in the federal list. How to read these figures.